on 08-07-2008 2:40 PM
Hi all,
I've a problem in trx KP06 for planning on cost element category 90 is it possible modify the standard from error message to warning?
Thanks!
Best regards,
Gaetano
Hi,
does it exist any possibility for planning or modify this message?
thanks
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
The system does not support other uses of category 90 cost elements. You cannot plan using these cost elements. You may be successful in changing the message, however, when the functionality itself is missing, it may not serve any purpose. You may play around t-codes like OBA5 to change message control, but am not sure.
Hi,
I was checking issues on cost element category 90 and came across your problem.
It is possible to plan a category 90 cost element. We can plan the cost element against "Capital Investment Order". Create an internal order with order type 0650 and release the order. Now in transaction code KPF6 it is possible to plan against the internal order.
Similarly, you can plan the cost element against Capital Investment WBS element. Follow the same path for planning.
Regards,
Amit
Category 90 is permitted only for internal orders and WBS elements
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
109 | |
15 | |
10 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.