on 12-23-2008 11:55 PM
Hi,
The planned values are showing in all the std. SAP reports.
But when passing the object number of the WBS element from PRPS in the RPSCO table for the planned cost.
Value type selected were 1 and 10 as well.
But still it is not showing any data.
I tried using the CJEN as well but no result.
Can any one please suggets on this please. I need to develope a report based on this planned cost.
Also from which table I can get the Project Duration in days.
Thank you
Check the customisation with the help of CO for the OPI1, OPI2 & OPI4 and finally run the consistancy chekc for your assignments of Tsn OPI2 & OPI4 by running CJVC.
Not sure but check with this tables COSP : primary costs ( Total records )
COSS : Secondary costs ( total records )
COEJ : ( Planned cost ) line itmes
I think, Project duration is the is not the field in the PROJ table, if you have the duration in days that you have to use field PLFAZ (start date) and PLSEZ ( finish date ).
For the WBS you can get the same data from PRTE table.
Regards
Nitin
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
97 | |
10 | |
8 | |
6 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.