Dear all,
Kindly find below image,in this al the raw materials are showing in Planned order,but it has to display as Sch line,purreq,po items.I dont know what changes i have done.kindly please let me know
Regards
Rajasekaran
Hi Raja,
Processing key NETCH
Create purchase req. 1
Schedule lines 3
Create MRP list 1
Planning mode 3
Pl check the above parameters in MRP run screen. MD01.
Also pl ensure, the Procurement key.
If it is "F" then its ok.
Or it is "X" then pl ensure Schedule agreement & Source list available.
Thanks
R Vaithiyanathan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello
Check the following note, which explains the most common causes for this kind of issue:
http://service.sap.com/sap/support/notes/1967840
The document below may also be useful:
If you are using an MRP group, check the creation indicator on transaction OPPR and make sure that it is set to generate schedule lines.
BR
Caetano