MRP planning error

former_member1241202
Active Participant
0 Kudos

Dear all,

Kindly find below image,in this al the raw materials are showing in Planned order,but it has to display as Sch line,purreq,po items.I dont know what changes i have done.kindly please let me know

Regards

Rajasekaran

View Entire Topic
former_member364899
Participant
0 Kudos

Hi Raja,

Processing key            NETCH

Create purchase req.      1

Schedule lines            3

Create MRP list           1

Planning mode             3

Pl check the above parameters in MRP run screen. MD01.

Also pl ensure, the Procurement key.

If it is "F" then its ok.

Or it is "X" then pl ensure Schedule agreement & Source list available.

Thanks

R Vaithiyanathan

Caetano
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hello

Check the following note, which explains the most common causes for this kind of issue:

http://service.sap.com/sap/support/notes/1967840

The document below may also be useful:

If you are using an MRP group, check the creation indicator on transaction OPPR and make sure that it is set to generate schedule lines.

BR

Caetano