I have a requirement where in I need to trigger the goods issue of the sales order item linked to the network header when a milestone is triggered through network activity confirmation. Any idea how this can be achieved through milestone functions or some other ways?
Thanks in advance.
Nithin.
Hi Nithin,
When a milestone is reached, you will enter the actual date of completion of that milestone in CJ20N. As soon as you put that and save it, the block will be released in the sales order and you can post a delivery and a goods issue for the items whose milestone block was released.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello Robin,
Thanks for the reply. However, I will have more than one milestones spanned across multiple networks which will then be multiple lines in my billing plan.
For Eg
Milestone 1 : Electrical Diagram Network 1
Milestone 2: Goods Issue Network 2
Milestone 3: Final Payment Network 2
Sales order
123456/10
Sales order billing plan here will have 3 lines. And I would prefer to trigger the delivery of the sales order item only if the
"Goods Issue" Milestone (Milestone 2) is triggerred and not for the remaining two. Now how can I achieve that?
Hope it is clear
Looking forward to the answer
Thanks in Advance.
Nithin.
That is right Nithin. So when you have a milestone with the corresponding WBS in CJ20N done, put in the actual date of completion in CJ20n and save. What this will do is that for that item to which this Milestone2 network/WBS has been assigned will get cleared from the block and hence we can clear those items for delivery.
These blaocks you can assign in the network template in the activities.