on 10-07-2008 2:11 PM
Hi
Client/Mfg have sub contracting vendor for their requirement.
Client dont hv any warehouse. So..
Vendor sending the FG directly to customer in Client named DC.
How to map this in SAP?
Regards
Ram
You can use Third party process for this scenario but if you are the one who provide the cmponent to the vendor than this will not work other wise it will work
Create PO with Third party item category to the vendor and ask him to deliver to the custom
the delivery address in the PO should be customer address
you than bill to customer and pay to the vendor
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Yes, third party process won't work with subcontracting in SAP (sorrowfully). Individual PO scenario may be a workaround:
http://help.sap.com/erp2005_ehp_03/helpdata/EN/dd/5601d4545a11d1a7020000e829fd11/frameset.htm
Regards,
Csaba