on 10-02-2009 7:36 AM
Dear Guru
In my Industries following case are done
1)- During release process order i am reserve 25 kg material.But during conformation COR6N i am change that material qty 25 to 20 kg becuase this material is backflush.but in system transition MB25 saws that you have still 5 kg open reservation.
2)- I am release process order & reserve qty 25 for material X which is not backflush.Our Mm member will issue this material Against process order using transition code MIGO.Then Production people go to Change Process order Using T-Code COR2 & change Quantity Of Material X.So In T-code MB25 We saw Negative Open reservation of material X
Please give me detail haw can we salve upper case.so we can clear reservation in MB25
Thanks
Pnakaj Kapadia
Dear guruji
when we confrom process order using t-code COR6N we change Qty of backflush material but still we getting problem to clear open reservation.we are using mile stone conformation.
Thanks
pankaj
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Pankaj,
1) When you are performing confirmation and when you are changing the quantity in Goods Movement screen, for the record activate the check box for Completed field. This would set the final Issue for this component, so there wont be any open reservation for this material.
Or in the Change mode of the order go to the components overview screen and for the component activate check box for "Fls" field (Final Issue) and save the order, this would also clear the reservation for the component.
I am not able to understand your 2nd scenario..please explain?
Regards,
Prasobh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.