on 2024 Oct 29 9:05 AM
Dear Team,
I am working on public cloud and need to restrict the production order release if work center capacity exceeds (I have already maintained checking control configuration) and also it will be helpful if you can share capacity evaluation & leveling public cloud document link.
Regards,
Tejas P.
Request clarification before answering.
Hi Tejas,
You can use Fiori Apps Capacity Scheduling Table, Capacity Scheduling Board and Manage Work Center Capacity to level the overload/capacity.
BR
SKAEAD