Dear Maciej,
you view capacity utilization you can use same line groups or work center groups together with the capacity scheduling board, to assign them between different work centers.
Capacity Scheduling Board | SAP Help Portal
Reschedule Operations through Drag and Drop | SAP Help Portal
How to view Capacity Utilization using Same Line Groups & Work Centers | SAP Help Portal
In this example added to work centers to one group to check their capacities.
Best regards
Dennis