Cancelled network activity confirmation but actual hours still capture

Former Member
0 Kudos

Dear all,

I have executed CN29 to cancel confirmation on the network activity and the status of the network activity is now REL, however there is 22.1 H still capture as actual and also there is forecast hours.

Could you please advise on this? How to remove the actual hours?

Thanks and regards,

Jessie

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi Jess,

First of all please check already booked approved hours details in CJI3 report like where they are booked and then try to cancel the approve hours.

Please find the below link : -

http://wiki.scn.sap.com/wiki/display/ERPHCM/Cancelation+of+Time+Sheet+Data

http://scn.sap.com/thread/1112145

Regards

Shashank

former_member201206
Active Contributor
0 Kudos

Hi Jessie,

does the activiy have any activity-elements? Otherwise it looks like inconsistent.

Kind regards,

Zhenbo

Former Member
0 Kudos

Hi Zhenbo,

No, there is no activity elements under this activity. What can I do in this case?

Thanks.

former_member201206
Active Contributor
0 Kudos

Hi Jessie,

I suppose, the table AFVV contains still the incorrect values of OFMNW & ISMNW. The mentioned correction report  ZZAFVV01 of note 146929 can clean the values.

Please let me known, if the report helps.

Kind regards from Germany,

Zhenbo

Former Member
0 Kudos

Hi Zhenbo,

I have implemented Note 1774633 and it works.

I have tried report ZZAFVV01 before and it works but this will be inconvenient for the users thus Note 1774633 is useful.