Hi experts,
I have created one ZMCR, which is copied from SMCR.
I processed it to "Being Implemented", under it I have one SMHF and one SMMJ. The SMHF is completed and the SMMJ is withdraw.
The ZMCR should be able to be confirmed, right? But in the action list, there are only "Extend Scope" and "Create BPCA analysis". I can't process it or put it back or withdraw it anymore.
Everything is just copied from standard and I didn't do any customizing.
Does anyone have suggestion, where I should check?
Thanks!
Kris
Kris,
The first thing to check is under Change Management->Standard Configuration->Change Request Management Framework->Make Settings for Change Transaction Types.
If I understand from your original message, you are creating standard Change Documents (SMHF and SMMJ) from a custom Request for Change (ZMCR). If so, check in the above configuration under SMHF and SMMJ and make sure under Specify Status Attributes->Specify Status Setting for Predecessor Documents you have ZMCR/E0005 as an entry for each Change Document 'closing' status, for example E0006 for SMMJ and E0008 for SMHF.. Note, you may need to add this entry for other Change Document types if you are using Admin (SMAD), etc. A standard entry for SMCR/E0005 should already exist in each case.
Note, it may be wiser to copy SMMJ and SMHF to Z versions and make the changes there: add the ZMCR/E0005 entry under the ZMMJ/ZMHF/etc.
Kindest regards
Paul
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Paul,
thanks for your reply!
Yes, I created a SMMJ from ZMCR, because I copied ZMCR from SMCR but I forgot to adjust the copy rule at that time, so SMMJ is automatically connected to ZMCR. I'll do the copy rule later. But anyhow, the ZMCR is just a copy of SMCR right now.
In the customizing, there is no such entry for SMMJ like you stated, ZMCR/E0005 or even SMCR/E0005. Please see the attachment.
Maybe you meant the entry like in the second screenshot for SMCR (ZMCR) should appear:
Thanks!
Kris
Hi all,
thanks for your help. problem solved!
Kris
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi,
At first you must use the report AI_CRM_CPY_PROCTYPE for copying transaction types to z space,
for smcr confirmation done automatically by adjusting status attributes,means when your uc closed, it confirmed the RFC too.
your case, we could see status attributes are wrong.
adjust the status attributes accordingly in your z transaction type. follow the example here, could help you much http://scn.sap.com/thread/3169894
Thanks
Jansi
Message was edited by: Jansi Rani Murugesan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks Jansi and Paul,
I think I figured out the reason based on your post. And yes, I did copy the transaction using report AI_CRM_CPY_PROCTYPE.
But I'm facing a related new problem. In order to test, I created one new ZMCR and inserted a ZMHF in scope. But as I released it for development, there is no Change Document for ZMHF generated. I don't know where to check it.
Could you help again?
Thanks!
Kris