Multi-level error propagation carried out in mrp live

ninad_narad
Active Participant
0 Kudos
377

Hi,

We are using embedded PP/DS on S4HANA 1809. All materials and WCs are advanced planning relevant.

When we run mrp live we are getting the error multi level error propagation carried out & all planned orders are also stuck in CCR. All inconsistencies are cleared from om17. Can you suggest a solution for this issue.

Regards,

Ninad

Accepted Solutions (1)

Accepted Solutions (1)

ninad_narad
Active Participant
0 Kudos

Hi,

The issue was resolved with implementing note 2603963. We are using S4 1809 with embedded PP/DS.

Regards,

Ninad Narad

Answers (1)

Answers (1)

Ruthvik_Chowdary
Active Contributor

Hi

Once you get Such error there is option called Solve Issue Materials in MRP Live (MD01N) and system will give exact issue and suggestions try that