Dear friends of TM,
In many order-to-cash scenarios it’s important for a supplier to confirm a delivery date to his customers already during the creation of a sales order. Thereby, the confirmed delivery date should be as reliable as possible to allow the customers to plan follow on processes based on that e.g. the pickup at a handover location or production processes.
In a scenario of a sales order being integrated with TM embedded in SAP S/4HANA, the calculation of delivery dates for schedule lines could happen as follows until now:
This has the following two challenges:
Now, with SAP S/4HANA 2023 FPS1 we tackled those challenges by introducing a TM scheduling based on the transport network of TM and its heuristics already when capturing the sales order in the system. So with that, transport related master data has only to be maintained once, in TM. And the calculated delivery dates are taken over in the freight units from which transport planning can then be done.
The basic interaction of the involved components in the TM based sales order scheduling is described in the following:
The following are the key features of the solution:
To set up the TM master data based scheduling, the following steps need to be executed:
As shown before, the TM master data based scheduling is integrated with the BPS application. This needs to be set up here:
A new profile has been introduced where a planning profile can be assigned and the means with which the TM scheduling should be performed. The new profile along with the available means to schedule are shown here:
During sales order creation the logistics integration profile is determined and the assigned transportation duration determination profile is then considered for the TM scheduling.
The functionality is shown with an example of the following scenario: A supplier delivers cargo to a customer with incoterm DDP, means the supplier is responsible for the transport to the customer incl. unloading of the cargo.
At first, the data of the respective sales order is captured:
After pressing 'ENTER' (or any other such action), the ATP check and the TM scheduling is called. The result incl. the calculated delivery date can be checked in the RACR screen:
You see, that we calculate the duration from the start of loading until the cargo arrives at the destination location. Unloading times are not considered.
The sales order can then be saved and a freight unit with the calculated delivery date is created:
So with that development, a long awaited feature now eventually found its way in SAP S/4HANA TM, increasing the value of the integration of sales orders with TM significantly. Furthermore, this feature supports customers on their transition from LE-TRA to TM.
Appreciate any feedback and comments!
Best regards,
Michael