Introduction:
The LE outbound delivery distributed to EWM will have the distribution status as B (Distributed). Once that is done, no change can be made to the LE delivery. To overcome this, we can use the function module /SPE/DELV_RESET_DIST_STATUS to change the distribution status to A (Relevant) or D (Planned for Distribution).
Process to change the delivery distribution status from B (Distributed) to A (Relevant) or D (Planned for Distribution):
STEP 1: Create the Outbound delivery and distribute it to EWM
The Distribution status is shown as B (distributed) at the delivery header.
STEP 2:
Now, navigate to Transaction code SE37.
Enter the function module /SPE/DELV_RESET_DIST_STATUS
Then execute.
STEP 3:
Click on the Value of the parameter IT_DELIVERY_KEYS and provide the delivery number. The Value for the parameter IV_NEW_DISTSTAT should be D (Planned for Distribution) and then executed.
The delivery distribution status is changed to D (Planned for Distribution) in the delivery.
STEP 4:
Similarly, we can change the delivery distribution status to A (Planned for Distribution) as shown below:
Conclusion:
Using function module /SPE/DELV_RESET_DIST_STATUS, we can change the distribution status to A (Relevant) or D (Planned for Distribution) from B (Distributed) for delivery.