Dear expert,

I want to implement when item DP Status changes, the status of the project phase changes.

I already know I need to activate the implementation /RPM/DES_POINT_WF of the BAdI definition /RPM/DECISION_POINT.

The problem I have now is that the 'activity' is emtpy in the following path,I don't know if this affects the functionality I mentioned above, or if this configuration is just for sending emails.

SPRO > SAP Portfolio and Project Management > Portfolio Management > Global Customizing > Global Settings > Workflow Settings >maintain configuration for workflow recipients

Let me know if anyone knows

best regards

Mian Wu

View Entire Topic
ravi_ekambaram
Product and Topic Expert
Product and Topic Expert

Hi Main Wu,

You can achieve this requirement of status synchronization from Item DP status to project phase using standard DFM (Decision Flow Management) configuration. Using DFM, you can synchronize status, attributes and authorization. Check below link for more details.

https://help.sap.com/saphelp_ppm610/helpdata/en/4a/c4078c744f246fe10000000a42189c/frameset.htm

Configuration path:

SPRO-->SAP PPM-->Common Functions-->Decision Flow Management Settings-->Status Synchronization.

Regards,

Ravi

0 Kudos

Thank you my friend, Your answer settled my question.I have a new problem now. Please help me if you know.

https://answers.sap.com/questions/13149379/sap-ppm-actual-cost-in-cproject-from-ps.html#