on 12-05-2016 6:34 AM
Dear Experts,
How can I activate Process variant for all Activities in a Network while activating the process variant on the network header.
Setting process variant at each activity level is a very cumbersome job.
Any Work Around?
Thanks
Abdul
check cmp2 cmp9 transaction if help you.
variant is nothing but when you execute the transaction with some specific input then save it will create as variant so no special setting for this whenever you run the transaction select the variant then execute outcome will come as you freeze in variant.
Regards,
Sanjeev