on 04-17-2019 9:22 AM
Hello,
I want to turn on AVC(control budget) for superior funds center, i.e for the funds centers that are not on the bottom of the funds center hierarchy. I'm planning budget normally, for the most bottom-level funds center, but requirement is that control should be on higher level.
Hi,
After changing settings in AVC, e.g. derivation strategy, you have to initialize the AVC ledgers by running FMAVCREINIT. And, of course, when you create a strategy, you have to assign it to FM area and the ledger in the customization. Also, you have to make sure that the new value overwrites the old one; there is an attribute in the target field, which you have to set on.
Regards,
Eli