WBS planned revenue was incorrectly captured from sales order in KKA2

0 Kudos

Hi expert:

I am facing a urgent question about KKA2 in my project. The WBS element was assigned one sales order item (just have one item), the system can accurately calculate planned revenue from billing plan for sales order item in KKA2。When the WBS element was assigned multi-sales orders or one sales order has multi-items,then the wbs element planned revenue can be double from billing plan for sales orders in KKA2. how can I solve this issue ,thanks in advance.

Accepted Solutions (0)

Answers (2)

Answers (2)

0 Kudos

please reference to below screen shot. the wbs element planned revenue is 35,398.24,but sales order item net value is 26,548.68. that is to say sales order 100000422 net value is double calculated.

Ken_Melching
Product and Topic Expert
Product and Topic Expert
0 Kudos

Planned revenue on a WBS comes from all of the Sales Order Items assigned to that WBS. If there are 10 Sales Order Items at 2000 each then the WBS sees 20,000 as planned revenue.

Is that what is happening?