on 04-27-2011 8:32 PM
Hi,
I have successfully run progress analysis using Estimate method . As my understanding after I run CNE1, system will record POC that I maintained in Estimate table into SKF. Which report I can use to see this SKF value ?
I have checked all SKF report in PS and even in Cost Center Accounting, but the report has no data.
Hi,
Execute 12EVA1 and 12EVA2 in CJE0.
Tnx.
Abdul