S4HANA Capacity levelling

raju_123
Participant
0 Kudos
199

Dear team, as you are aware, we run mrp and then cm25 capacity levelling seperately in ecc. Please advise whether we can do material availablity planning and capacity levelling at a time in s4hana without using ppds system? Please advise what steps we need to follow both in s4hana and in ppds systems. Appreciated.

View Entire Topic
raju_123
Participant
0 Kudos

Thank you Sasi for the response. So, in S4HANA material planning and capacity levelling is like 2 step planning (material planning first and then capacity planning separately). But in classic PPDS, we can do both material planning and capacity levelling in single planning run. is my understanding correct?