on 12-02-2008 6:56 AM
Hi All,
I need to update Cost Centers and Profit Centers in existing Projects(CJ20N).
Actually when the Projects were created Cost Centers and Profit Centers were not given. Now the customer needs them to be given there.
Do let me know if there is any tool or method I can use for updating the same.
Also clarify whether it can be done through LSMW or not.
Regards,
Raj Kumar Reddy.
can use LSMW - that is actually the best option
use CJ07 and CJ12 for project def and WBS respectively for your recording
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.