on 04-10-2023 1:03 PM
In my scenario, Plant B will purchase Raw material from Plant A ( which is under same company code ) through STO process and Plant B will ship that Raw material to Subcon vendor so that Plant B will receive finished material .
But here Plant B will create STO PO towards Plant A for Raw Material but material from Plant A should be directly delivered to Subcon Vendor, Now Invoice and Payment will be done done by Plant B only towards Plant A.
And in Last Plant B will create Subcon PO for finished material towards Subcon Vendor and now he Plant B will not issue raw material to Subcon vendor as material is directly delivered from Plant A to Subcon vendor , Plant B will receive Finished Material with Byproduct as a Production loss from Subcon Vendor.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Try 2nd option as mentioned above by creating an address number in MEAN and enter that address number in STO Delivery Address TAB.