on 06-25-2017 3:10 AM
Dear All,
I got a PO against contract that was created when the contract had a validy period. So in the material data tab button Components I need to change the plant and Prod.sto.loc, just it, but when I try to save a standard message "Target value of contract XXXX exceeded by XXXXX" (Message no. 06042) appears as error and dont let me save the change.
In the contract I got target value = 7.913.444,19 and net value = 7.909.662,82
Appear like when I open PO to edit, it is like got value from contract again. For some itens I got the changes did, but for others I was not possible to change.
Contract validity end = 31.05.2017
PO was created on = 12.05.2017
Someone could me help with it?
Unfortunately there are 11 OSS notes mit program fixes created in 2017 and 2016 only, it could potentially be a bug what you see.
If your basis system is a kind up to date then you can use PANKS and it will help you to find the notes that need to be implemented, see this blog which explains this function: https://blogs.sap.com/2014/11/28/got-an-error-message-the-new-tool-panks-is-here-to-help-you/
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
9 | |
8 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.