Dear Team,
Please suggests the best solution for the below issue.
Issue: Maintenance Plan generated for an equipment for frequency monthly for 2 years with order completion check mandatory.
start date: 01-01-2015
one order generated after that no any order generated from last 6 months, as first order till not completed by the user.
so, now what we will do as per best suggestion and best practice.
If we close the first order then system generates second order for the month of feb. but I want this months order. any suggestion Please.
thanks
Sushant
Dear Sushant
can you brief this point
If we close the first order then system generates second order for the month of feb. but I want this months order. any suggestion Please.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Sushant,
what are the scheduling Parameter maintain in MP, The call depend upon thi sparameter please paste scheduling parameter screen shot.
Tolerence and shift factor will determine the nest call date.
If you Complet Order say by (07.07.2015) and change Shift factor to 100% Before scheduling in IP30/IP10 and schedule system will generate order for 07.08.2015 based on scheduling parametr (Tolerence +/- = 0, and Call Horizaon =0)
Rgds,
Sunil