Hy SAP Community Good day!

I want to plan the Material Cost Estimate without Quantity structure at Network like production order, want to calculate variances/WIP but when i make cost estimate with KKPAN tcode with cost sheet/costing variant assignment planning cost of KKPAN is not shown at network order.

Question is.

1. SAP allow planning cost estimate with network order like production order

2.if yes then how can i book this cost on network.

3. if above two are not possible then how can i book plan cost at network

Reply waiting.

View Entire Topic
BalasubramanianAP
Active Contributor
0 Kudos

Hi,

1. SAP allows planning cost estimate with network order like production order:

Yes. We have lot of options like Easy Cost Planning (CJ9ECP), network cost planning (CJ9K) etc.

But we may not do with KKPAN (which is used for FG).

Please check this WIKI PAGE: https://wiki.scn.sap.com/wiki/display/PLM/Easy+Cost+Planning+in+PS

You can also check this answer link:

https://answers.sap.com/questions/5707899/project-costing-net-working-costing.html

We can do WIP in PS. You can check the below answer for that:

https://answers.sap.com/questions/4907935/configaration-steps-of-wip-calculation-of-wbs-elem.html

waqas81
Explorer
0 Kudos

Great its seem to be relevant let me implement than will assign you Points. Thanks for Sharing