hello,
I have two materials with the same number but one has an empty valuation type with price A and the other has a valuation type C1 with price B, I input the material in iw32 but the price recorded from material valuation type empty.
What should I do, so i can input material in iw32 that get price from material valuation C1
Thank You
In the material reservation in the work order, input your valuation type C1 in the "batch" field and see the effect.
Regards,
Vijay