Cure time/Quarantine time in SAP Public Cloud

ranjithjoy
Participant
0 Kudos
256

Hi,

I have a requirement where a product needs to be in quarantine for 94 hours after production before inspection can be allowed. How can I do this in Public Cloud?

View Entire Topic
Enda
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hi ,

 

In S/4HANA Cloud we have the inspection lot 03 (inspection during production)

but the possibility to specific Quarantine days is not available

 

Best Regards

Enda