Dear all experts,

I noticed there are some differences between the 2 screens when you run CK11N or CK13N when you display Cost Estimate of a material:

1. Left: Costing Structure View

2. Right: Itemization View

As you can see from the screenshot above, the 4 highlighted items are having zero Total Value in <Costing Structure> view while the same items are having the correct values (non-zero) in <Itemization> View.

Where is the source for both views when the cost estimate is performed?

Thank you.

Sincerely,

Sebastian

chengshiong_kwan
Participant
0 Kudos

Anyone experienced this before?

Thanks.

View Entire Topic
feng_dong
Employee
Employee

Hi Sebastian,

Looks like the cost estimate for the relative material in the BOM is deleted, so it's shown as 0 in the costint structure view.
But the itemization is saved in the DB, so it will be shown correctly.
Did you face some message like CK375 when displaying the cost estimate?