AMC Process

john_steven
Explorer
0 Kudos

Hi All,

My Customer needs AMC to be configured. But right now they don't have any standard process. So what will be the best process? Also let me know the steps for configuring this process?

Thanks a lot for your help in advance.

Client needs AMC for the following scenarios

i) Includes only Machine services.

ii) Includes Machine services and spares.

Regards,

Steven

View Entire Topic
Former Member
0 Kudos

Hi

As I understand that you need following two types of Maintanance contracts

1, Comprehencive (with spares)

2, Non-comprehencive (without spares).

You have to create two type on Service contract documents refering to "WV/SC" doc. type.

Maintaian all condition types and condition records for the services and spares refering to the following link:

"http://help.sap.com/saphelp_46c/helpdata/en/ae/6480d1d08011d2b5380000e8a4bb0c/frameset.htm"

After configuring all , also set up resource related billing (DP90) for the contracts, if needed.

please explore by refering to the above link.

It must be of defenite use.

reagrds

DSR

Edited by: D.Srinivasa Rao on Oct 28, 2011 11:29 AM

john_steven
Explorer
0 Kudos

Hi Srinivas,

I check that link, but i am unable to understand the process completely.

Can you please let me know the steps to configure the AMC process for the below scenarios.

i) Includes only Machine services.

ii) Includes Machine services and spares.

I am new to CS process so request you to help me. Also let me know the in which parts PM integration is required for AMC process.

Thank you very much for your help in advance.

Regards,

Steven

john_steven
Explorer
0 Kudos

Hi,

I am working on AMC process. Please confirm me whether the process mentioned below is correct or not? Also let me know if there are any changes required.

Service contract will be created as per the requirement.

As per the service contract the Service task list will be created

Service task list will be assigned to the Service Maintenance plan with Duration

As per the Duration the Service Maintenance plan will release the Service order

Process the Service order as per the Task list operation

Capture the required data related to Service Charges, Spare parts used, Travelling Expenditure & Other Charges

Confirm the Service order.

Create a Billing Request.

Create a Billing document

Settling & Complete the Service Order.

Display the Planned /Actual Cost of Service Order.

Regards,

Steven

hasan_ahmed1
Active Participant
0 Kudos

Hi Steven,

The above said process is correct.

Let me know if you have come across any issues while configuration.

Thanks

Mohammed