Can some one help me with a sample scnario for Progress Analysis which can help in understanding what events will lead to Cost Variance or schedule Variance and will give me EAC, ETC etc.
I have all the settings done for progress analysis, but I am getting same values for BCWP & ACWP.
Also, how is Plan POC related to schedule/duration/period of the activity?
Regards,
VDS
Dear Rupesh,
please have a look at the SAP online documentation following this link:
http://help.sap.com/saphelp_erp60/helpdata/en/b4/ba853488601e33e10000009b38f83b/frameset.htm
Project Progress -> Progress Analysis:
There you can find a list with the relevant KPI's, formulas and questions they will help to answer.
Project Progress -> Progress Analysis Progress:
There you can find a short scenario with a diagramm which explains the cost variance and schedule variance.
The relation of the POC calculation to values like schedule/duration/period is depending on the measurement method which is used, as every measurement method uses different values as basis for the calculation. So a general answer can't be given on that.
Kind regards,
Dirk
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
The standard reports offer various values we can use to assess the progress of the project. The following fields are defined in the standard progress analysis reports:
- Planned POC in percent
- Actual POC in percent
- Budget Cost of Work Schedule, BCWS
- Budget Cost of Work Performed, BCWP
- Cost variance (CV)
- Schedule variance (SV)
- Value index (CPI)
- Estimated costs at completion (EAC)
Regards,
Raj
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
116 | |
8 | |
6 | |
6 | |
6 | |
6 | |
5 | |
5 | |
4 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.