on 08-12-2013 8:07 AM
Hi,
My business is facing one issue where the Net value of contract is some 3800 KWD. and the milestone billing net value is 3500 Kwd.
I don't understand why this issue of price difference has come now. I checked other documents in SE16 (VBAK table) with same document type and billing type, they are picking the same value. No data inconsistency found.
Please guide what could be the reason?
I tried to cancel the billing document and redo the billing, then in update button select option D.
But that option it self is not available!
Hi,
Since it is a milestone billing, you can to compare the Billing dates with the Dates in the Sales order at Billing plan tab
i believe there could be two Billing plan dates in which you billed only one
can you compare these dates? if possible provide the screenshot of Billing plan tab from the sales order item
regards,
santosh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Repeat Post - But still my question remains the same :
"Could you please share the screen print of your Billing Plan tab of your Contract ?"
Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
109 | |
15 | |
10 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.