on 03-28-2008 11:13 AM
hi,
sap gurus,
how to configure shipment document
step by step
configureation steps is needed
regards,
balaji.t
09990019711
>
> hi,
>
> sap gurus,
>
> how to configure shipment document
>
> step by step
>
> configureation steps is needed
>
> regards,
>
> balaji.t
> 09990019711
Hi Balaji,
Shipment costing steps
1) Create Purchase Contract TCode ME31K
Put the Vendor, Agreement Type, Purch Org, Purch Group
2)In the contract put the Target Value and Validity end date
Press Enter
a) Choose the Text Item category the field "i" generally it would be service
b) Choose Acct assg Category Field "A"
c) Enter short Text
d) Enter Material Group
Press Enter
a) Put Short Text
b) Enter Unit of Measure Field "U"
c) Enter Price
Save Contract is created
3) Release the contract (Release + Save)
4)Create a Standing PO ME21n
a) Put Purchasing org
b) Purch Group
c) Company code in Org Data tab
Go to Additional data tab
Put Validity start and End
Go to limits put limits
Go to customer data in Header and put PO approvers name.
Save the PO.
5) Release the PO ME29N
Release the PO and Save
Now create Shipment Cost
1) Vi01
Put shipment category
Shipment number
Inside the Shipment cost the status will be C, B, A initially for Calculated Assigned and Transferred respectively
Save the shipment cost document.
Reward if helpful
Regards
Abhishek
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
96 | |
8 | |
5 | |
5 | |
4 | |
4 | |
3 | |
2 | |
2 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.