Hi Experts,
When i enter the plant name in project definition and save it at once, am getting the following error message,
"Factory calendar in project differs from plant factory calendar
Message no. CJ707"
Its not allowing me to save the project at all. I am able to only cancel and come out of the project.
Please advise.
Thanks & Regards,
Kabir
Issue is Solved. PP plant customised calendar and PS Calendar in project profile was Corrected and Matched.
Edited by: Kabir on Feb 2, 2009 12:26 PM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I feel it is due to pogramming error. Please refer SAP note 627481
Regards
Nitin
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
109 | |
15 | |
10 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.