Has anyone experienced direct/indirect labor entries doubling or tripling the daily totals after entry??
Example: I enter time confirmations using IW44 - Save.
When I check IW47 to review the daily calculations of my entries, each confirmation displays multiple times as if I entered the same info 2 or 3 different times.
I know IW44 is a little tricky compared to IW41 (single confirmation entry), but it's been happening all week.
Any ideas of what may cause this??
Are they using IW42 based on a WO because this can cause multiple Time Cnfirmation on save if they don't remove the Operation not to be confirmed.