Different starting months for operations in single Maintenance Plan

former_member245085
Participant
0 Kudos
280

Hi Expert,


I have the below PM requirement for Equipment on the strategy base plan.

  • Task List Operation 1: Monthly JAN, FEB, MAR,.......
  • Task List Operation 2: Two monthly FEB, APR, JUN,.......
  • Task List Operation 3: Three monthly JAN, APR, JUL,.....

Can we do this in a single Maintenance Plan without creating multiple plan to same equipment?

Thanks

Ashok M

Accepted Solutions (1)

Accepted Solutions (1)

Vaibhav-Mishra
Active Participant
0 Kudos

Hello ashok.malhotra,

There is a feature of Offset in maintenance strategy which can be used to delay the start of a certain maintenanc cycle related to a particular operation.

Vaibhav

former_member245085
Participant
0 Kudos

Thanks vaibhaverp,

It works 🙂

AM

Answers (1)

Answers (1)

Vaibhav-Mishra
Active Participant
0 Kudos

Hello Ashok,

You can go with maintenance strategy plan for different cycles for each operation.

Vaibhav

former_member245085
Participant
0 Kudos

Hi Mishra,

Thanks, but How to specify that only Operation 2 should start in FEB When the whole plan starts in JAN?

AM