on 08-18-2007 2:17 PM
Hi,
I am facing problems w.r.t. update of customer down payment in project info systems. As per standard SAP, after doing customer down payments, this will get updated in project info systems (CN41/CN41N).
Please suggest me to fix the issue.
Best Regards,
Ranjan
Hi Biplab,
In the planning profile u ve to tick mark a check box that says automatic revenue update from sales order. secondly let me clear u sth that a down payment never updates actual revenue in a project.
regards
sunil kar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi,
Downpayment request is used to create a billing request through
the t code DP 90.This DR can further be used to create a billing document
say invoice.
Actually you will be using these fundas in Resource Related Billing because that is
where the integration between PS and SD module take place with the help of
DR against actual resource utilized in the project.
I hope this clarifies your question and award points if it is so.
Do not hesitate to ask me if you have any further questions in this.
Thanking you,
Best Regards,
R.Srinivasan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.