on 09-17-2008 6:11 AM
While doing costing run
To manfacture 1 No finished product, we require 6 Nos raw materials with each qty 1No.
But while doing costing for finished products the raw materials qty costed for 1.09 EA for all the Raw Materials
I have not maintained any Scrap Data
Any settings to be changed or technical problem
Murali
Dear Murali,
What was the exact issue?How did you solve it?
Can you reply regarding this.
Regards
Mangalraj.S
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Murali,
check in the material Master data of your finished product whether have you maintained any assembly
scrap & for raw materials whether have you maintained any component scrap in the material master or any
operation scrap in the BOM.
Check what's the item category type of that raw material say whether is it a stock item L or a variable size
item R.If it's a varaibale size item then as per the formula defined it will pick the cost.
Please check these details and revert back.
Regards
Mangalraj.S
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Murali Mohan,
check the Costing Lot size which you give in CK11N and also the base quantity of the BOM header.
Goto T code CS03,enter the finished product for which you are trying to do the cost calculation,press on
F6 button that's header and check the base quantity.Say if it's 2,then whatever the components which are
assigned in the BOM is required to produce 2 quantity of the finished product.So as per this the cost also
will get calculated.
Please check & revert back.
Regards
Mangalraj.S
User | Count |
---|---|
101 | |
12 | |
10 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.