I want to know how to choose the type of confirmation for control keys for operations mainly for MES.
And what is meant by Milestone confirmation ? Confirmation required ? Confirmation not possible ? Possible but not necessary ?
In which step this can be used ?
Thanks for your help.
Regards,
Carole
Dear,
For MES you can just use the control key with Mile stone operation for the last operation and the confirmation required for the previous operations.When you send the confirmation for the last operation from MES all the previous operations will be automatically confirmed
Thanks,
Naresh.