#CoE#SDHX how to Allocate manufacturing costs to Subcontracting

omega-ou
Participant
0 Kudos

Hi SAP experts,

The business scenario is as follows:

In the Subcontracting business, we need to send materials to suppliers for outsourcing processing, and before sending materials, the materials need to undergo simple processing within our company. We do not want to set up a new BOM for this internal processing, but we hope to allocate the internal labor and manufacturing costs of the processing to this Subcontracting order.

Currently, Subcontracting can add expenses from external suppliers, but how to allocate internal expenses ?The amount of allocated expenses is calculated manually outside the system, but how to allocate it to Subcontracting orders in SAP?

OwenLiu
Product and Topic Expert
Product and Topic Expert
0 Kudos

Removed irrelevant tags.

Accepted Solutions (1)

Accepted Solutions (1)

OwenLiu
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hi Rujia,

You can consider to use overhead for the production order.

BR, Owen

omega-ou
Participant
0 Kudos

Hi,

Thanks for your reply. You mean that use the production order ,and set the first process as internal processing and the second process as outsourcing processing ?

OwenLiu
Product and Topic Expert
Product and Topic Expert
0 Kudos

for internal process, you should either create operation, or use overhead cost.

Still suggest you to follow the standard suggestion from scope item.

omega-ou
Participant
0 Kudos

Hi ,

Thanks.

Answers (0)