CJ20N v CJ20 (Adding to an existing structure by copying from a template)

Former Member
0 Kudos

Hi

CJ20 supports adding to an existing structure by copying from a template.

This can be done by clicking on the WBS Basic Data tab and then following the menu path:

Project > Copy From

You can then copy from a Template or Operative Structure.

I have tried to find this really useful functionality in transaction CJ20N - Project Builder however it does not appear to exist.

Does anyone know how this can be done using the project builder.

Thanks

Ian

View Entire Topic
Former Member
0 Kudos

Hi

In CJ20N right click on WBS and then click "include". You will find the same screen. Another way to include structure is in CJ02.

Regards