on 04-11-2014 11:35 AM
Hello All,
I have integrated the SAP PS with CATS and I want to know which all reports i can use to confirm the PS transfer is successful.
As soon as the CAT5 is run and time is transferred i want a report for the confirmations of the transfer is successful.
I am trying to use the CJI3 but that report is not clear because it does not give the informations on the hours transferred, and
many times i get no line items to be selected.
Why i get no line items selected when i pass the project ID in CJI3. ??
Regards,
Lohith
Try transaction COFC, if no errors, it means the postings are good.
CJI3 should also work. Pull the fields Total Quantity, UOM and Business Transaction and filter it out by RKL, you should be able to find the line items for CATS posting.
Hope it helps.
Thanks,
Hilton
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Although this is trivial, please check the selection of CJI3 and the filtering of CATSPS.
Also, are you using standard DB profile or you use your own?
Also, is there any archiving exercise has been done before on the CATSPS table?
If they are all good, suggest you log an incident to SAP OSS for diagnosis.
Thanks,
Hilton
Hi...
you should check table CATSPS that holds the intermediate records...A separate column (TRANSFER) Indicates if records were transfered to target component PS...(the same applies with CATSCO table and transfer CO)..
Check it and let us know
Panagiotis
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Lohith,
I am not very much sure but could you please check report CADO ?
Regards,
Amit
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
96 | |
10 | |
10 | |
5 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.