on 08-13-2015 5:21 AM
Dear Gurus,
After doing the monthly cost planning using CJR2, is there any way from where I can do the budgeting the monthly basis Or it should be done only on yearly or Overall basis.?
Regards,
M.Reddy
Hi,
No, it cannot be done on monthly basis. It can only be done on Overall or Yearly basis.
Regards,
Amit
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Yes you could release the budget on monthly basis but you need to run this 12 times in a year( i.e for every month). Another approach would be to implement the Funds Management module where you can control your payment and commitment budget on monthly basis based on combination of commitment item, fund center and WBS element.
Regards,
Amit