Activation of Budget commitment for project orders (MD51-generated)

0 Kudos

Hi

We are creating project planning orders through MD51 against components maintained in project and converting planning orders into Purchase requisitions through MD14. But it is not getting triggered to commitment either for planning order or for purchase requisition . But commitment is getting triggered in case we have created Purchase requisitions directly.

I request you provide configuration if any to activate budget commitment for project orders (which were generated through MD51)

Accepted Solutions (0)

Answers (3)

Answers (3)

Paulo_Vitoriano
Active Contributor
0 Kudos

Hi Krishna,

Maybe you should check COOI table directly or run CJI5 without dates restriction.

Also you can share your OPSV settings with a screen shot.

Regards,

Paulo

0 Kudos

Hi Paulo Vitariono,

Thank you very much for your response .

we have already maintained settings in OPSV against Order category. But it is not getting populated commitment .

Paulo_Vitoriano
Active Contributor
0 Kudos

Hi Krishna,

Please revisit your OPSV settings. I believe it is the order category 10.