We have some finished materials that we are using strategy 52 to forecast and purchase the raw materials before sales orders are received.
We are trying to limit sales to our forecast both with quantity and date of production, but only when we hav...
Working with a new consultant that doesn't know much about MRP groups,
Is it possible to use MRP groups to allow a single finished good to have different strategy groups within different MRP areas
is strategy group one of the settings with in MRP...
Hello all,
We product goods in two configurations, built, we will call sku 6000 (1 finished good) and unbuilt we will call 1000,2000,3000 (3 finished goods)
Is there a was to configure the BOMs, and planning strategies so we can forecast only at ...
Hello,
We are exploring the use of the "Discontinued Parts" function within MRP 4 in our new system.
We have 4 FERT BOMs that use ROH X, within MRP 4 for material X we have
Discontin. ind. = 1 Eff.-out =4/1/20 Follow-up matl = Material Y
Aft...
Hello Raja, I appreciate you responses and, I understand what you're saying about trying to about trying to start final production without waiting, let me explain a little deeperwe have products that have, high cost, long leadtime >120 days but short...
Hello RajaIn case of the Planning Strategy 52, once you receive the Sales Order, during the MRP Run, System will look for the existing VP Planned Orders, in that period, if exists, system will convert that VP Planned Order, to the Convertible Planned...
Cartano, thank you for your responseaccording to this SAP help document https://help.sap.com/saphelp_470/helpdata/en/81/470a58ddab11d1b55b0000e82de178/frameset.htmVSE are a valid requirement type within a MRP area, but then it seems to directly contr...
Hello rupesh.brahmankar3->The material to be discontinued is not discontinued using MRP.- I don't believe this is the case, which setting should I check to confirm?see my comment to Raja about my MRP run and planning the materialsI don't believe the ...
1) yes, sorry I am performing "Read PP Master Data" while in create production order from clicking on convert planned order from MD042) from above, yes the productions orders are brand new being created.before running the MRP test I manually deleted ...