cancel
Showing results for 
Search instead for 
Did you mean: 

Multiple Preq. generated after MRP run

Glenn
Discoverer
0 Kudos
69

Hi MRP Guro

We have set up a Plant 1360 / SLoc 200A Plant 1360, SLoc 200A, MRP is generating multiple Requisitions to buy material from vendor, when MRP is set as Z3, SM03 & a safety stock value of zero. (which should only order material when there is a requisition from the field.). Previously this Plant is just generating 1 requisition after the MRP run but now it generated multiple requisition, 

Can you advise how we can fix this issue, The current MRP type is Z3 and lot size is TB with forecasting  period indicator of "M".

Hoping for your immediate response.

 

Thank You

Glenn

Accepted Solutions (0)

Answers (0)