on ā2024 Apr 15 11:37 AM
Hello
i have a question in capacity report
in resource utilization - capacity field
can anyone explain how the capacity is calculated
thanks
Request clarification before answering.
Hello Mohammad
When you access /sapapo/cdps_rept > resource utilization, there is a field called 'capacity'. This field means:
"The unit of measurement for the capacity requirement, the total capacity and the free capacity is:
- In the case of single-activity and single mixed resources: Hours
- In the case of multi-activity resources und multi-mixed resources: Hours x Unit of measurement for the capacity of the multi-activity resource"
This information can also be found in the F1 help.
Best regards
SAP Support
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
| User | Count |
|---|---|
| 17 | |
| 16 | |
| 6 | |
| 3 | |
| 2 | |
| 1 | |
| 1 | |
| 1 | |
| 1 | |
| 1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.