Capacity report (/SAPAPO/CDPS_REPT)

Mohamed-abdelqa
Newcomer

Accepted Solutions (0)

Answers (1)

Answers (1)

yasmin_alayyan
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hello Mohammad

When you access /sapapo/cdps_rept > resource utilization, there is a field called 'capacity'. This field means:

"The unit of measurement for the capacity requirement, the total capacity and the free capacity is:
- In the case of single-activity and single mixed resources: Hours
- In the case of multi-activity resources und multi-mixed resources: Hours x Unit of measurement for the capacity of the multi-activity resource"

 

This information can also be found in the F1 help.

Best regards

SAP Support