2015 Sep 10 1:06 PM
Dear Friends,
I have a dbm service order with more than one task and the labor item in the task is only one.
I would like to book time against task and not against item. So would like to know can we book time for task without item in it.
Please help
Thanks & Regards,
Manoj Bind
2015 Sep 11 10:20 AM
HI Manoj,
No, SAP do cost posting of labor ( time punching from /DBM/TM_VT ) items from cats to DBM header internal order via secondary cost element which is re-posted to split internal order while billing. Since task do not have items its not part of any billing and hence SAP cannot do this cost re-posting.
Regards
Ganesh
2015 Sep 10 1:28 PM
Hi Manoj,
You need to configure the time clocking to be done at the task level rather than the item level.
please configure /DBM/SPRO - > Service -> Time Management -> Determination of criteria for use of time management -> Define criteria for sales organisation.
Here you can define the time clocking at the task level.
Regards,
Sachin Balmiki
2015 Sep 11 9:27 AM
HI Sachin,
Thanks for the clarification we have done that but my query is that can we book time for a task without an item in dbm service order.
Regards,
Manoj Bind
2015 Sep 11 10:20 AM
HI Manoj,
No, SAP do cost posting of labor ( time punching from /DBM/TM_VT ) items from cats to DBM header internal order via secondary cost element which is re-posted to split internal order while billing. Since task do not have items its not part of any billing and hence SAP cannot do this cost re-posting.
Regards
Ganesh
2015 Sep 11 10:41 AM
HI Ganesh,
Thank you for making it clear, I have a business scenario where i have only one labour item and 3 task. And I want to book time for task and not against the item.
Business scenario: 3 tasks are performed for that single labour item. and we want to book time for the task. How can we achieve this using SAP Standard.
Thanks & Regards,
Manoj
2015 Sep 11 11:21 AM
Hi Manoj,
Mapping between task to item is one to many not many to many. So quick solution that I can suggest is to created two more dummy labor text items with zero price. This way you will have three tasks assigned to three items. This will help you in reporting also .
Regards,
Ganesh
2015 Sep 11 12:06 PM
HI Ganesh,
Thank you for the confirmation I was thinking to do so and wanted to double check with experts in this area.
Thank you once again.
Regards,
Manoj