Dear Team,

I would like to integrate SAP PPM with IM and PS where in I would to like get IM position budget for my PPM buckets and Items to have PS budget trasfer from IM.

Could you advise if this is std intergation or we need to build custmized interface for same?

Also, advise me how I can connect PPM bucket with corresponding IM position in SAP and how to report back budget figures at bucket level?

Regards

Atul

Accepted Solutions (1)

Accepted Solutions (1)

Ken_Melching
Product and Topic Expert
Product and Topic Expert
0 Kudos

It would require a custom interface mainly since IM and PPM (the portfolio side) have completely overlapping functionality.

There is standard functionality to transfer the Porfolio Item budget to the PS Project budget for Budget Availability control.