Project structure not transfered correctly from PPM to PS

ennouhif95
Explorer

Accepted Solutions (1)

Accepted Solutions (1)

SAP231
Product and Topic Expert
Product and Topic Expert
0 Likes

Hello,

You have created a task directly under the project definition followed by Phase 1 hence its apearing end of the project. You need to create to create the PPM project in the following manner:

Project Definition

Phase

Task

Milestone

Please try out above option.

Thanks

Amit

ennouhif95
Explorer
0 Likes

Thank you !