Total Cost Commitment in CN41N report

Shahzad_Ahmed
Explorer
0 Kudos
238

Total cost commitment column in Report CN41N is blank after creating the purchase order from purchase requisition. The amount is displayed in Plan cost but "Total Cost Commitment" column is still blank. How can I configure the purchase order amount as "Commitment" in MM or Project System.

 

 

View Entire Topic
sumesh_gupta
Active Participant

Hello @Shahzad_Ahmed Please check once if commitement management is active for controlling area in OKKP t-code.

Regards,
Sumesh Gupta 

Shahzad_Ahmed
Explorer
0 Kudos
I have checked, Commitment management is active in Controlling area configuration in OKKP