Total Cost Commitment in CN41N report

Shahzad_Ahmed
Explorer
0 Kudos
435

Total cost commitment column in Report CN41N is blank after creating the purchase order from purchase requisition. The amount is displayed in Plan cost but "Total Cost Commitment" column is still blank. How can I configure the purchase order amount as "Commitment" in MM or Project System.

 

 

Accepted Solutions (1)

Accepted Solutions (1)

sumesh_gupta
Active Participant

Hello @Shahzad_Ahmed Please check once if commitement management is active for controlling area in OKKP t-code.

Regards,
Sumesh Gupta 

Shahzad_Ahmed
Explorer
0 Kudos
I have checked, Commitment management is active in Controlling area configuration in OKKP

Answers (1)

Answers (1)

MarcioBlos
Active Participant
0 Kudos

Hi @Shahzad_Ahmed 

Do the G/L accounts used in the purchase document have a cost element? Did they exist before the creation of the purchase document?

Try executing the CJEN transaction to restructure the RPSCO table of the project.

Regards,
Marcio Blos